How to estimate

Use actual face dimensions plus planned mortar joints to estimate coverage.

Worked example

An 8 by 16 inch nominal module covers 128 square inches; 100 sq ft needs about 113 modules before allowance.

Distinguish nominal and actual dimensions

A nominal module may already include the mortar joint. Adding a joint to nominal dimensions again understates the block count.

Round the order

For 100 square feet and a 128-square-inch module, the unrounded count is 112.5. With 10% allowance the count is 124 blocks.

Identify special units

Corners, bond beams and openings can require different units. Obtain a project-specific masonry schedule rather than relying on total face area.

Worked project example

A 20 by 6 ft wall face covers 120 sq ft. With a nominal 8 by 16 inch module, the area estimate is 135 units before allowance.

Compare purchasing costs

At 5% extra, round up to 142 units. At an illustrative $2.50 per unit the subtotal is $355.

Common estimating mistakes

Area counts do not establish reinforcement, footing, bond or structural requirements. Obtain an approved layout.

Frequently asked question

Are corner units included? Not automatically; count special units separately.

Before ordering

Structural wall design and special blocks require separate planning.

Open the free calculator →

Planning estimates only; confirm project requirements with qualified professionals.