Estimating Paver Base Volume
How to estimate
Multiply area by the specified compacted depth and convert to cubic yards.
Worked example
150 sq ft at 4 inches gives 50 cubic feet or 1.85 cubic yards of compacted volume.
Separate base layers
Calculate each specified layer independently. Do not combine bedding sand and aggregate into one volume estimate.
Compare volume scenarios
For 150 square feet, a 4-inch layer is 1.85 cubic yards and a 6-inch layer is 2.78 cubic yards. These are examples, not design recommendations.
Confirm compaction conversion
Ask the supplier for loose-to-compacted volume guidance for the selected aggregate. Site drainage and base design require separate assessment.
Worked project example
For 216 sq ft and a specified 4-inch layer, geometric volume is 72 cubic feet or 2.67 cubic yards.
Compare purchasing costs
If the supplier specifies an illustrative loose-volume factor of 1.2, the purchase estimate is 3.2 cubic yards before order rounding.
Common estimating mistakes
Do not assume a universal compaction factor or use this calculator to select structural base thickness.
Frequently asked question
Should bedding material be included? Calculate it as a separate specified layer.
Before ordering
Ask suppliers how loose delivery volume relates to compacted volume.
Open the free calculator →Planning estimates only; confirm project requirements with qualified professionals.